Trucell Installation Advice
aluminium open cell ceiling
NotesSAS Emac hangers must be used in conjunction with Emac hanger brackets for intallations at 1500mm centres max.Emac hangers should be installed a maximum of 300mm from the edge of the system. Where two main runners are clipped together, an Emac hanger should be installed within 300mm. It is considered good practice to stagger joints in supporting structures. Additional LoadsThe Trucell system can support additional loads such as services up to a limit of 3kg. This limit is based on a point or uniformly distributed load over over 0.36m_, positioned a minimum of 1000mm apart.Trucell panels can be pre-ordered with enlarged cells to accept luminaire trays, supplied by either the luminaire manufacturer or SAS International. For further advice please contact the SAS technical department. |